Highway Achievements

Name of Project Amount
(In Million)
KPRRP  Phase-I 70.27 km 548.681
Phase-II 59.50 km 628.102
Phase-III 55.50 km 689.358
Phase-IV 54.65 km 602.406
Phase-V 50.50 km 618.102
Construction & Extension of Pattan Minara Manthar Road  (Length: 26.25 K.M) 338.453
Construction of approach road from Iqbalabad to Indus Bridge (L: 22.73 Km) 970.546
Construction of Flyover Bridge at Abbasia Town Railway Crossing 692.343
Widening / Improvement of road from Belgium Chowk to Bypass(L:  4.25 KM) 362
Construction of Flyover at Feroza Railway station (Length:- 2500 Rft) 374.41
Construction / rehabilitation of Road from Khanpur to Bago-Bahar, Tehsil khanpur (Length:-  24.00 KM) 352.163
Widening / Improvement of Palace Road from Pull Dari Sangi To U.A.E Palace (L:- 12.00 K.M). 912.12
Dual Carriageway from Allahabad (Old Tehsil Headquarter) to Liaquatpur (Tehsil Headquarter). (Length: 6.00 Km) 453.383
COMMUNITY DEVELOPMENT PROGRAMME (19 No. Schemes) 222
RURAL ACCESSIBILITY PROGRAM PHASE-I (9-No. Schemes) 870.661
SUGAR CANE DEVELOPMENT CESS FUNDS (61 No. Schemes) 873.625
PUNJAB MUNCIPAL SERVICES PROGRAMME (PHASE-I) (24-No. Schemes) 167.199
Construction of Fly Over at Feroza 508.302
Dualization of Metalled Road from Thalli Chowk Rahim Yar Khan to Iqbalabad (N-5) District R.Y.Khan In Progress
Construction of Flyover at Khanpur In Progress
Construction of Approaches on both sides of Sheikh Khalifa Bridge (UAE) over River Indus alongwith Guide Banks District Rahim Yar Khan. In Progress